Building

To construct several buildings, including the reactor building, PALLAS partners with its main contractor (General Contractor). This phase of the project is the most extensive part of the works. The General Contractor is expected to be definitively selected in November 2023. From the end of 2024, the General Contractor will take over the works from BESIX, the contractor contracted for the Pit & Foundation phase.

General Contractor Selection 

The selection of the General Contractor is conducted in 3 phases, starting from 24 January 2023. The agreement between PALLAS and a selected partner will be signed at the end of November 2023. 

placeholder afbeelding
Mar 6, 2023
Deadline submission
placeholder afbeelding
Mar 29, 2023
Selection decision

placeholder afbeelding
Apr 13, 2023
Start dialogue phase
placeholder afbeelding
Jul 20, 2023
End of the dialogue meetings

placeholder afbeelding
Aug 25, 2023
Start offer phase
placeholder afbeelding
Sep 29, 2023
Deadlines for submission offers
placeholder afbeelding
Nov 1, 2023
Award decision
placeholder afbeelding
Nov 30, 2023
Anticipated agreement execution date

Lay down area
Lay down area
Phase 1
Pit & Foundation
Pit & Foundation
Phase 2
Building
Building
Phase 3
Completion
Completion
Phase 4